Name of the Project | : | Batang – Semarang Toll Road (75km) |
Total Investment | : | Rp 11.050 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | Private |
Location | : | Batang, Central Java |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | November 2016 |
Planned Commercial Operation Date | : | October 2018 |
Latest Status | : | Construction Section I & II (Batang – East Batang) – (East Batang– Weleri) 3,93% Section III (Weleri – Kendal) 3,66% Section IV & V (Kendal – Kaliwungu) – (Kaliwungu – Semarang) 4,61% Total 4,14% Land Section I (Batang – Batang Timur) 100% Section II (Batang Timur – Weleri)74,57% Section III (Weleri – Kendal) 10,53% Section IV (Kendal – Kaliwungu) 34,35% Section V (Kaliwungu – Semarang) 71,83% Total 57,62% |