| Name of the Project | : | Cross- Border Post (PLBN) Development & Its Supporting Facilities, Mota’ain, Belu District |
| Total Investment | : | RP. 82.070.900.000 |
| APBN-APBD Source | : | State Budget |
| Private Source | : | – |
| Source Not Yet Determined | : | – |
| Funding Scheme | : | State Budget |
| Location | : | Belu, East Nusa Tenggara |
| Implementing Agency | : | Ministry of Public Works and Public Housing |
| Planned Construction Commencement Date | : | 03 August 2015 |
| Planned Commercial Operation Date | : | 26 October 2016 |
| Latest Status | : | Financial Progress has achieved 100 %
Construction Progress has achieved 100 % |
Description of Project
Work package of PLBN development in Mota’ain consists of development of the Main Building, Arrival Cargo Inspection, Departure Cargo Inspection, Carwash Building/ disinfectant, Weighbridge Building, Truck Scanning, Arrival Fountain and Red and White Flag, Garuda Monumen, Pump House, Tasbara Gate (Guard House)