Name of the Project : Medan- Kualanamu-Lubuk Pakam-Tebing Tinggi Toll Road (62km)
Total Investment : Rp 4,072 Trillion
APBN-APBD Source :
Private Source :
Source Not Yet Determined :
Funding Scheme : Private
Location : Medan, North Sumatera
Implementing Agency : Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority
Planned Construction Commencement Date : 2015
Planned Commercial Operation Date : 2017
Latest Status : Progress of Land Acquisition :
Section I (Medan-Kualanamu), 17,8 Km : 88,90%
Section II (Kualanamu-T.Tinggi), 43,9 Km : 84,27%
Total : 86,37%Construction Progress:
Section I & II (53,19)
Section III (92,92%)
Section IV (53,25%)
Section V(41,33%)
Section VI (41,13%)
Section VII 0%
Total of BUJT 42,13%
Total (45,32%)

 

Description of Project

Medan- Kualanamu-Lubuk Pakam-Tebing Tinggi Toll Road is planned to connect Medan – Tebing tinggi and Kuala Namu Internasional Airport (KNIA).