Name of the Project | : | Kunciran-Serpong Toll Road(11,19km) |
Total Investment | : | Rp 2,623 Trillion |
APBN-APBD Source | : | – |
Private Source | : | – |
Source Not Yet Determined | : | – |
Funding Scheme | : | – |
Location | : | Tangerang, Banten |
Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
Planned Construction Commencement Date | : | 2017 |
Planned Commercial Operation Date | : | 2019 |
Latest Status | : | Land Progress • Section 1 (South Tangerang), 9,90 Km : 26,46% • Section 2 (Tangerang), 4,30 Km : 63,23% • Total : 32,63% Construction Progress No Construction progress has been made |