| Name of the Project | : | Cinere – Jagorawi Toll Road (14,64km) |
| Total Investment | : | Rp 2,621 Trillion |
| APBN-APBD Source | : | – |
| Private Source | : | – |
| Source Not Yet Determined | : | – |
| Funding Scheme | : | Private |
| Location | : | North Jakarta, The Province of Special Capital Territory of Jakarta (DKI Jakarta) |
| Implementing Agency | : | Ministry of Public Works and Public Housing c.q. Indonesia Toll Road Authority |
| Planned Construction Commencement Date | : | August 2010 |
| Planned Commercial Operation Date | : | 2019 |
| Latest Status | : | Land Progress
• Section 1 (Jagorawi – Raya Bogor), 3,70 Km : 94,01% |