Name of the Project : Cross- Border Post (PLBN) Development & Its Supporting Facilities, Skouw, Jayapura
Total Investment : RP. 165.944.300.000
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : State Budget
Location : Jayapura, Papua
Implementing Agency : Ministry of Public Works and Public Housing
Planned Construction Commencement Date : 18 December 2015
Planned Commercial Operation Date : 15 December 2016
Latest Status : Financial Progress has achieved 94,12 %

Construction Progress has achieved 97,20 %

Description of Project

Work package of PLBN development in Skow consists of the Main Building, Integrated Arrival Inspection Building, Clinic, Carwash Building/disinfectant, Weighbridge Building, Kennel, Utility Building, Check Point Building and Tasbara Monument.