Name of the Project : Construction of the New International Airport at Yogyakarta Special Region Province
Total Investment : Rp. 9 Trillion
APBN-APBD Source : State Budget
Private Source :
Source Not Yet Determined :
Funding Scheme : State-Owned Enterprise
Location : Kulon Progo,  Yogyakarta Special Region
Implementing Agency : PT Angkasa Pura I
Planned Construction Commencement Date : July 2017
Planned Commercial Operation Date : 2020
Latest Status :
 

Coordination Meeting with Regional Development Planning Agency of the Special Region of Yogyakarta (Bappeda DIY) in relation to the plan to relocate the citizens who will be affected by the construction of the International Airport of Yogyakarta has been held.

Appraisal bidding has been undertaken and processed by PT Angkasa Pura (Persero) Branch Office in Yogyakarta and the winner of the bidding is Muttaqin Bambang Purwanto Rozak Uswatun & Partners
Consulting Services for Valuation and Professional Property Economics (KJPP). The appraisal determination will be carried out by the National Land Agency (BPN). The appraisal team will start its field work after the handing over of field map and nominative list. The determination will be carried out by Chief Exeutive of Land Procurement to the winner of the KJPP Team

Description of Project

Construction of airport with the capacity of 14 million passengers per year, 28 airplanes and it has 3.250 m2 x 45 m2runway. .